How long does the Development Application process take for a house and land estate in NSW?
The Development Application (DA) process for a house and land estate in NSW can vary significantly depending on the size, complexity, and local council, but here’s a general breakdown:
| Stage | Average Duration |
|---|---|
| Pre-lodgement planning & documentation | 1–3 months |
| DA submission to council | 1 day |
| Initial council assessment | 1–2 weeks |
| Public exhibition / notification (if required) | 2–4 weeks |
| Final assessment & referrals | 4–8 weeks |
| Determination (approval or refusal) | 6–12 weeks (total) |
| If referred to planning panel or JRPP | Add 4–8 weeks |
Total estimated timeframe: 3 to 6 months (at most times it would be far longer than that)