How long does the Development Application process take for a house and land estate in NSW?

The Development Application (DA) process for a house and land estate in NSW can vary significantly depending on the size, complexity, and local council, but here’s a general breakdown:

Stage Average Duration
Pre-lodgement planning & documentation 1–3 months
DA submission to council 1 day
Initial council assessment 1–2 weeks
Public exhibition / notification (if required) 2–4 weeks
Final assessment & referrals 4–8 weeks
Determination (approval or refusal) 6–12 weeks (total)
If referred to planning panel or JRPP Add 4–8 weeks

Total estimated timeframe: 3 to 6 months (at most times it would be far longer than that)